It can be observed that these penalties are in an A.P. having first term as 200 and common difference as 50.
a=200, d=50
Sum upto n terms (Sn) = n/2[2a + (n-1)d]
Penalty that has to be paid if he has delayed the work by 30 days = S30
S30 = 30/2[2(200) + (30-1)50] = 15[400 + 1450] = 15(1850) = 27750
Therefore, the contractor has to pay Rs 27750 as penalty.